Skip to main content

6. Working with the simulation

in Getting started
Authors list
Published: Mar 8, 2024|Last updated: Nov 5, 2024

6. Working with the simulationCopy link to 6. Working with the simulation to clipboard

Now you are all set to go to the simulation visualization view. On the top navigation bar, switch to the home view.

You will be asked to run setup sequence. A setup sequence is a function that configures the parameters of a simulation model, preparing the system with initial conditions and making it ready to run. Click Run and wait till sequence will finish.

Simulation itemsCopy link to Simulation items to clipboard

Depending on the scenario, you'll find items from the table below.

Icon

Element

How to interact

breaker_open breaker_closed

Breakers

Use the right mouse button to toggle the breaker between open and closed. Pressing the scroll button will put you into force mode, allowing you to control the breakers over the controls.

Battery Load Mains PV

Battery, Loads, Mains, PV

To set the values for load, mains, battery or pv click on them with the left mouse button. This will then open a panel into which you can enter the appropriate values.

easygen easyi gc ls6

easYgen, easyI, GC, LS6

For all types of devices, it is possible to overwrite the values of digital inputs. To do this, press the left mouse button on the device, a list of all DIs will be displayed. To overwrite the value of a DI click on the name DI_X to switch between 0/1 values.

genset diode line

Genset, diode, lines

Read only elements

Exercise:Copy link to Exercise: to clipboard

As an exercise, let's try an experiment.

  1. Set Load:

    • Active power: 10kW

    • Reactive power: 10kW

  2. Set Mains:

    • Voltage: 400V

    • Frequency: 50Hz

  3. Set Load Breaker (LB)

    • Close breaker

  4. Set easYgen

    • Activate DI_6 - Release MCB

  5. Wait around 30 seconds and observe simulation.

  6. Set Mains:

    • Voltage: 0V

    • Frequency: 0Hz

  7. Wait around 30 seconds and observe simulation.

After all the steps, Generator 1 should start to turn off, Mainc Circuit Breaker (MCB) should close and Generator Circuit Breaker (GCB) should open. In this way, we manually switched the power supply to the mains. Then when the voltage on the Mains drops, easyGen should automatically start the generator back up, and switch power to the generator. The scenario after all steps should look more or less like this: